Status Tabs Definitions

It is important to understand that every recommendation has three key dates:

  • The ‘Initial Exam Date’ is the date of the radiology exam that produced the follow-up recommendation
  • The ‘Min Due Date’ is the earliest date that a follow-up must be performed per the radiologists’ recommendation (i.e. if the radiologist recommends a follow-up in 3-6 months, Min Due Date would be 3 months)
  • The ‘Max Due Date’ is the latest date that a follow-up must be performed per the radiologists’ recommendation (i.e. if the radiologist recommends a follow-up in 3-6 months, Max Due Date would be 6 months)

We use these dates to build out a timeline for each unique follow-up recommendation and to group each recommendation into tabs at the top of the ‘Follow-Ups” page:

Status TabDefinitions Per ACR ‘Follow-Up Improvement Collaborative’
Non-MatureAll recommendations between ‘Initial Exam Date’ and ‘Min Due Date’ minus 30 days.
Coming DueAll recommendations between ‘Min Due Date’ minus 30 days and ‘Max Due Date’
OverdueAll recommendations between ‘Max Due Date’ and 60 days after ‘Max Due Date’
Non-CompliantThe follow-up recommendation remains incomplete 60 days after ‘Max Due Date’
AdherentThe follow-up exam is completed between ‘Min Due Date’ minus 30 days and 60 days after ‘Max Due Date’
Completed Before/After TimeframeThe follow-up exam is completed before ‘Min Due Date’ minus 30 days OR beyond 60 days after ‘Max Due Date’.
ScheduledThe follow-up exam is scheduled but not completed
Manually ReviewedThe navigator has manually updated the status of the recommendation via the ‘Action Status’ dropdown. This includes:

Acknowledged
Not Clinically Necessary
Completed Elsewhere
Patient Deceased
Unsubscribed
Navigator Closed
Needs Prior Auth
Needs Prescription

Please note that once a user manually changes the status, we no longer update the status automatically on a time basis. However, we will update the status to Adherent, Completed before/after, and Scheduled if any of those events occur.